施工圍擋的使用嚴(yán)禁干什么?
來(lái)源:http://www.davylee.cn/ 發(fā)布時(shí)間:2022-12-13
圍擋一般為鋼架結(jié)構(gòu),金屬焊接成框架,是由方管、角鋼、鍍鋅板、噴繪畫(huà)面制作而成。那么施工圍擋的使用嚴(yán)禁干什么?下面濟(jì)南圍擋廠家為您講解一番。
The enclosure is generally a steel frame structure, and the metal is welded into a frame, which is made of square tubes, angle steel, galvanized plates, and painting pictures. Then what is strictly forbidden to use construction fence? Next, Jinan enclosure manufacturer will explain it to you.
1、嚴(yán)禁使用彩條布做圍擋。
1. It is strictly prohibited to use colored strip cloth as fence.
2、市政府要求,嚴(yán)禁使用竹笆、彩條布做圍擋;嚴(yán)禁毛竹搭架?chē)鷵跏┕?嚴(yán)禁使用編織袋、彩塑板圍擋施工;嚴(yán)禁圍擋破損、污倒、固定性差;嚴(yán)禁圍擋版面未經(jīng)批準(zhǔn)出現(xiàn)商業(yè)廣告或宣傳本企業(yè)廣告畫(huà)面內(nèi)容。
2. As required by the municipal government, it is strictly prohibited to use bamboo fences and colored strip cloth as fences; It is strictly prohibited to erect bamboo fence for construction; It is strictly prohibited to use woven bags and colored plastic plates for enclosure construction; It is strictly forbidden to damage the fence, dump the fence, or have poor safety and fixation; It is strictly prohibited to enclose commercial advertisements or publicize the content of the enterprise's advertising pictures without approval.
3、圍擋審批方面,城市道路主管部門(mén)在審批臨街店面裝修臨時(shí)占道和市政工程道路挖掘時(shí),須明確施工圍擋的設(shè)置標(biāo)準(zhǔn)、時(shí)間、范圍,同時(shí)將審批內(nèi)容抄送道路養(yǎng)護(hù)部門(mén)和城管執(zhí)法部門(mén)。
3. In terms of enclosure approval, when approving temporary road occupation for street storefront decoration and municipal engineering road excavation, urban road authorities must specify the setting standard, time and scope of construction enclosures, and copy the approval content to road maintenance departments and urban management law enforcement departments.
基礎(chǔ)施工過(guò)程中要隨時(shí)注意地下管線情況,如有管線處盡量繞開(kāi),不能繞開(kāi)的位置對(duì)管線采取保護(hù)性措施,嚴(yán)禁野蠻施工,如對(duì)地下管線造成破壞,后果自負(fù)。
During the foundation construction, pay attention to the situation of underground pipelines at any time. If there are pipelines, try to bypass them, and take protective measures for the pipelines where they can't be bypassed. It is strictly prohibited to carry out brutal construction. If the underground pipelines are damaged, the consequences shall be borne by yourself.
圍擋骨架(即圍擋主立柱)施工須等基礎(chǔ)砼養(yǎng)護(hù)達(dá)到一定強(qiáng)度后,按照?qǐng)D紙間距測(cè)放出立柱位置,圍擋安設(shè)人員按照測(cè)放出的立柱位置安設(shè)立柱,立柱安設(shè)好后采用角鋼均勻間距把立桿連接成整體,連接采用焊機(jī)焊接方式。須保證立桿的穩(wěn)定與牢固。
After the curing of foundation concrete reaches a certain strength, the construction of enclosure framework (i.e. enclosure main column) shall be carried out according to the spacing in the drawing. The professional enclosure installation personnel shall install the column according to the location of the measured column. After the column is installed, the angle steel shall be used to connect the column into a whole with even spacing, and the welding method shall be used for connection. The stability and firmness of the upright shall be ensured.
嚴(yán)格把材料采購(gòu)質(zhì)量關(guān),確保進(jìn)場(chǎng)的材料質(zhì)量滿足圍擋制作要求。施工圍擋的地腳螺栓要有一定的長(zhǎng)度,(不小于10cm)以增加圍擋與地面的錨固力。
Strictly control the quality of material procurement to ensure that the quality of materials entering the site meets the requirements for enclosure fabrication. The anchor bolts of the construction enclosure shall have a certain length (not less than 10cm) to increase the anchoring force between the enclosure and the ground.
圍擋主立柱方籠或者方鋼焊接須牢固,在安裝前由項(xiàng)目部技術(shù)人員進(jìn)行檢查,檢查合格后才可進(jìn)行施工。施工圍擋板面制作要求尺寸下料合理,封板整齊無(wú)縫隙,以名刮傷畫(huà)面。
The square cage or square steel of the main column of the enclosure must be firmly welded. Before installation, the technicians of the Project Department shall inspect it. The construction can be started only after the inspection is qualified. The fabrication of the construction fence plate surface requires reasonable size blanking, and the sealing plate is neat without gaps, so as to scratch the picture.
圍擋施工完成后安排專人負(fù)責(zé)對(duì)圍擋的螺栓、焊接等連接部位進(jìn)行檢查,如發(fā)現(xiàn)松動(dòng)部位,及時(shí)進(jìn)行加固或返工處理。更多相關(guān)內(nèi)容就來(lái)我們網(wǎng)站http://www.davylee.cn進(jìn)行咨詢了解吧!
After the enclosure construction is completed, special personnel shall be arranged to inspect the connection parts such as bolts and welding of the enclosure. If any loose parts are found, they shall be reinforced or reworked in a timely manner. More relevant content will come to our website http://www.davylee.cn Consult and understand!